The “All Zeroes One” Code Prevents Lost A/P Invoices

Oct 16, 2017 | Cost Controls, News, SJCC, White Paper

Executive Summary: A key component of job cost reporting is accurate posting of accounts payable (A/P). The time between receiving the invoice in the mail and posting it to your job cost reports can be fatal to a job, or a company. The answer is to not let the invoice out of the main office until it’s been posted to the project. Use the “all zeroes one” code to capture this cost in a job immediately.

The Problem: Invoice arrival at your office is a result of the United States Postal Service and your vendors’ billing cycles – and you cannot really control either party. But, this isn’t the problem – the problem starts when the invoice finally does arrive and it’s on you to manage the invoice through the Labyrinth of Processing to ensure it gets posted to the correct job in a timely fashion.

The danger zone is that period of time between the letter opener hitting that invoice envelope and the day the invoice gets coded to a job. If you’re not getting A/P posted in a timely manner to the projects, this leads to:

·  Inaccurate job costs
·  Inability to forecast working capital
·  Loss of credibility with the bank and a reduced line of credit
·  Decreased bonding capacity

The posting of an invoice to a project is often delayed because it gets

·  Lost in the corporate office
·  Delayed by the project manager because he/she has not cost coded it
·  Lost on its way back to the corporate office
·  Lost by the A/P department
·  Miscoded due to a data entry error by the A/P Department

The Solution:  All invoices stay in the vault until they’re coded to the All Zeroes One code! By now you’re asking two questions, the first being “what is this All Zeroes One code?”. The answer is this new cost code you see below which should exist in every single one of your projects (number of digits and dashes vary per accounting system):

00-00-0001 Outstanding Accts. Payable

The second question is “what is the vault?”, and here’s that answer:

Vault = your main office where invoices are received;
more specifically, your A/P department

If you can get your purchasers to, at a minimum, assign a job number to each purchase, the A/P staff can get every invoice into your job cost system immediately.

In conclusion, your A/P process remains the same except that you add a step to enter all invoices in the job, under cost code 00-00-0001 Outstanding Accts. Payable until it returns from the field. This process will ensure that all accounts payable is posted in a timely fashion and that job projections can be done with confidence.

 

Recent Articles

Increase Profit by Rule of 27

Increase Profit by Rule of 27

Executive Summary.  Most decisions can be further analyzed by collaborative or self-inquiry.  When looking for ways to decrease costs, ask yourself...

read more
Daily Cost and the What-If

Daily Cost and the What-If

Executive Summary.  Paramount to cost control is a superintendent’s and project manager’s ability to know cost in real time.  Knowing the daily cost...

read more

Leave A Comment

0 Comments